Electrical Project | Ottawa Hospital
Tuesday, 03 January 2017 by Power Systems Technology Staff
This new addition to the General hospital was to be powered by the double ended substation from another building. The plan was to increase the size of the two transformers and switchgear in the main complex and run two 600 volt feeders to the new building. The Problem By increasing the size of the existing
No Comments
Brockville Psychiatric Hospital
Tuesday, 03 January 2017 by Power Systems Technology Staff
The project involved the transferring of generator systems onto a medium voltage distribution loop. The system had to detect a loss of power from the utility, disconnect the utility then start the generators, step up the voltage and transfer it to the hospital. This was originally designed to be a line- up of medium voltage